Overview:
To address power shortages in and around New York City, local utility
ConEd (Consolidated Edison Company of New York, Inc.) executed a power
purchase agreement (PPA) with Astoria Energy, LLC, which agreed to
construct the first half – 500 megawatts (MW) – of a planned
1,000 MW electric generating facility. The approximately $800MM in
financing was the first refinancing of a Term B Loan transaction.
Construction started in April 2004 and was completed in May 2006.
E3 Services Provided:
- Provided support in the full and sole underwriting of financing
by an international bank, including the due diligence review for
the underwriting
- Provided Astoria and its lenders comprehensive monitoring services
during construction and start-up phases of the project
Project Spotlights:
- E3 project team secured private equity, construction
financing, including permanent debt for the first new large power
plant built near New York City in 25 years.
- Refinancing took place while the project was under construction
- Utilized 100 percent New York union labor
- Complete demolition and removal of a previously existing fuel
oil terminal on the site
- Installed two heat recovery steam generators delivered prefabricated
to the site
- Installed prefabricated pipe racks fully loaded with insulated
pipe
- Installed air-cooled condenser delivered prefabricated to the
site in easily erected modules
- Completed the project using an engineering,
procurement and construction (EPC) contract